07 February Construction Status

REALIZED WORKS

07.02.2022 – A block 3rd floor column, curtain and parapet were manufactured and concrete was poured.

08.02.2022 – B block Ground Floor slab was manufactured and concrete was poured.
09.02.2022 – C block 4th floor slab was manufactured and concrete was poured.
10.02.2022 – B block 1st floor column, curtain and parapet were manufactured and concrete was poured.
11.02.2022 – C block 5th floor slab manufacturing has been completed and the concrete has been poured.
C block wall production continues. 2nd Floor
C block plaster production started