CEBECI TOWERS WEEKLY ANNUAL REPORT
14.02.2022 – 20.02.2022
REALIZED WORKS
14.02.2022 – A block 3rd floor slab was manufactured and concrete was poured.
15.02.2022 – B block 1st floor slab was manufactured and concrete was poured.
15.02.2022 – A block 4th floor column, curtain and parapet were manufactured and concrete was poured.
16.02.2022 – B block 2nd floor column, curtain and parapet were manufactured and concrete was poured.
16.02.2022 – C block 5th floor slab was manufactured and concrete was poured.
18.02.2022 – C block 6th floor column, curtain and parapet were manufactured and concrete was poured.
20.02.2022 – A block 4th floor slab manufacturing has been completed and the concrete has been poured.
C block 2nd floor wall production continues.
20.02.2022 – A Block wall production started.
C block 1st floor plaster production continues.