21 February Construction Status

21.02.2022 – 27.02.2022

REALIZED WORKS

21.02.2022 – B block 2nd floor slab was manufactured and concrete was poured.
21.02.2022 – A block 5th floor column, curtain and parapet were manufactured and concrete was poured.
22.02.2022 – B block 3rd floor column, curtain and parapet were manufactured and concrete was poured.
22.02.2022 – A block 5th floor elevator curtain was manufactured and concrete was poured.
23.02.2022 – B block 3rd floor elevator curtain was manufactured and concrete was poured.
23.02.2022 – C block 6th deck was manufactured and concrete was poured.
25.02.2022 – C block 7th floor column, curtain and parapet were manufactured and concrete was poured.
26.02.2022 – A block 5th floor slab was manufactured and concrete was poured.
C block 3rd floor wall production continues.
C block 1st floor plaster production continues.
A Block 1st floor wall production continues.

To Top