24.01.2022 – A block 1st floor column, curtain and parapet were manufactured and concrete was poured.
27.01.2022 – C block 2nd floor slab was manufactured and concrete was poured.
28.01.2022 – C block 3rd floor column, curtain and parapet were manufactured and concrete was poured.
29.01.2022 – B block 1. Basement floor slab was manufactured and concrete was poured.
29.01.2022 – A block 1st floor slab manufacturing has been completed and its concrete has been poured.
30.01.2022 – A block 2nd floor column, curtain and parapet constructions were made and concrete was poured.