01.02.2022 – B block ground floor column, curtain and parapet were manufactured and concrete was poured.
02.02.2022 – C block 3rd floor slab was manufactured and concrete was poured.
02.02.2022 – B block ground floor columns and curtains were manufactured and concrete was poured.
04.02.2022 – C block 4th floor column, curtain and parapet were manufactured and concrete was poured.
04.02.2022 – Pumice wall material came to the field and c block was taken to the 1st floor.